An idea worth €20,000 a year that waits 60 days for a decision costs about €3,288, even if it is implemented in the end. That is the cost of delay: the idea's daily value times the days it waits. Below: a simple model for controlling, worked examples on hypothetical data and a portfolio view.
Why does decision time in a suggestion system have a price?
Cost of Delay is a way of communicating the impact of time on the outcomes we hope to achieve (1). Don Reinertsen, a cost-of-delay expert, advises (quoted by ProductPlan): "If you only quantify one thing, quantify the cost of delay" (2).
The Maersk Line example described by Black Swan Farming shows the scale. The Cost of Delay of a single feature there was more than $200,000 per week, and the 38 weeks it spent waiting in queues cost the organisation nearly $8m in lost revenue (1).
A suggestion system works the same way: a ready idea sits in a queue and the saving does not happen in the meantime. Back in 2004, the author of a Fast Company piece wrote about routinely coming across idea backlogs of several years, and about a general manager at a Fortune company who still had ideas on his desk from more than ten years earlier (5).
For opportunity cost in general, see our article on opportunity cost in processes. Here we measure one thing: what each day of waiting costs.
How do you calculate the cost of delay for an idea?
The model has three parts.
- Value over time. Take the estimated annual saving from the submission and convert it to a daily figure (divide by 365) or a monthly one (divide by 12). Black Swan Farming recommends expressing Cost of Delay per unit of time, usually in $/week or $/month (4). For the estimate itself, see how to calculate the ROI of an employee idea.
- Urgency profile. Many kaizen improvements, such as a lasting energy or material saving, fit the long life-cycle profile whose peak is unaffected by delay. The ramp-up and peak of benefits are effectively the same whether the solution is late or not (3). In that case the cost of delay grows linearly with every day.
- Days of delay. Count only the days on which the idea could already be working but is not: waiting for review, for a decision and for implementation to start. Leave out the implementation work itself.
Formula for the linear profile: cost of delay = (annual saving / 365) × days of delay. Monthly version: monthly value × months of waiting.
Example 1: a single idea (hypothetical data)
Example: an operator suggests a change to furnace settings that the department estimates at €20,000 in annual savings. That is about €1,667 per month, or about €54.79 per day. The submission waits 60 days for the committee's decision. The cost of delay is €54.79 × 60 days, or about €3,288. The monthly shortcut (€1,667 × 2) gives about €3,333, a negligible difference.
Example 2: the whole portfolio (hypothetical data)
Example: 25 ideas with an average value of €7,000 a year are in the queue, and the average waiting time is 60 days. The total cost of delay is about €28,767. If the average wait fell to 20 days, the cost would be about €9,589, a difference of about €19,178.
Which idea should you approve first?
With limited implementation capacity, use CD3 (Cost of Delay Divided by Duration): the cost of delay divided by the duration of the work (1).
Example (hypothetical data): three ideas are waiting for the same process engineer.
- Idea A: €13,000 a year, i.e. €250 per week, 4 weeks to implement, CD3 = 62.5.
- Idea B: €39,000 a year, i.e. €750 per week, 10 weeks to implement, CD3 = 75.
- Idea C: €6,500 a year, i.e. €125 per week, 1 week to implement, CD3 = 125.
The order C, B, A gives a total cost of delay of €12,125. The "by submission number" order A, B, C gives €13,375. The €1,250 difference comes purely from sequencing, even though the team does the same work.
Common mistakes when calculating cost of delay
- Counting all the time since submission. Implementation work is not delay; measure waiting between statuses.
- Inflated estimates. Report the value verified by finance; treat the submitter's estimate as preliminary.
- Assuming linearity where there is none. For a requirement with a hard deadline, the cost of delay is zero until the point where work needs to start (3). With a short life-cycle, being late reduces the peak benefits (3).
- Ignoring the hidden cost. Gallup reports that nearly half of employees who believe their opinions count at work say their current job brings out their most creative ideas. For those who are neutral or negative on that item, only 8% feel their creativity is encouraged (6).
How do you measure cost of delay in CostWise?
The model needs the idea's value and the dates of status changes. In CostWise the submission form has a field for estimated annual savings with currency, and the workflow Submitted → Under Review → Approved → In Implementation → Implemented keeps a full change history. The history shows how many days a submission spent in each status, and you can export submission data to Excel and multiply the days by the idea's daily value there.
The second lever is speed. Every status change sends a configurable email notification in the recipient's language. When the Manager enters the implementation date, the system automatically calculates a speed bonus. On the problem exchange (marketplace), managers publish specific challenges, and every employee proposal is linked to the problem it addresses. After implementation, the financial controller approves the verified saving in the financial workflow, so the model can use settled figures, not just estimates.